During power system operation, when a near external short-circuit fault occurs at the transformer outlet, instantaneous short-circuit surge current up to dozens of times the rated value generates enormous electric repulsion and axial compressive force inside the transformer. This can easily cause distortion, bulging, axial instability or disc displacement of high-voltage and low-voltage windings.
For many transformers with slight winding deformation, abnormalities can hardly be detected by conventional insulation resistance and DC resistance tests. However, once re-energized, the weak points with mechanical deformation will suffer insulation breakdown under alternating electromagnetic vibration, which may lead to severe phase-to-phase short circuit and transformer burnout within a few days.
In accordance with national power industry standards and State Grid anti-accident technical specifications, the low-voltage short-circuit impedance test is the most effective and direct non-destructive physical detection method for on-site judgment of transformer mechanical winding deformation.
Nevertheless, traditional on-site short-circuit impedance tests often require a high-capacity three-phase 380V high-power industrial frequency power supply or bulky large voltage regulators. It is frequently difficult to obtain such power supplies at newly-built outdoor substations or accident sites.
Manufactured by Baoding Huazheng Electric Manufacturing Co., Ltd., the HZZH-5 integrated transformer tester realizes high-precision fully automatic measurement of transformer short-circuit impedance with a lightweight single-phase low-voltage power supply.
Directly powered by single-phase 220V mains power, free switching between internal and external power sources The impedance test module of HZZH-5 adopts a sophisticated high-precision sampling and power conversion solution: Test with ordinary 220V mains supply: only a common single-phase AC 220V maintenance power supply on site is required. With the built-in low-voltage test source (switch the panel to "Internal Power"), the instrument can automatically apply test current to the transformer and collect data; Compatible with external voltage regulators for extended capacity: an "Internal/External Power Selector Switch" is arranged on the panel. For extra-large-capacity transformers or transformers with extremely high impedance that demand greater test capacity, simply switch to "External Power" to conveniently connect an external high-power voltage regulator for testing; High-precision voltage and current acquisition: the voltage measurement range covers 5V ~ 400V, and the current measurement range covers 0.1A ~ 10A, both with accuracy class 0.2.
Automatic sequential testing via three-phase wiring, one-click calculation of impedance error percentage For three-phase transformers with various vector groups including Y/△, Y/Y and △/Y: After reliably short-circuiting the secondary side, testers connect the test leads to the high-voltage terminals of the transformer in one go; Once the automatic three-phase test starts, the instrument sequentially excites AB, BC and CA windings, synchronously collects current and terminal voltage, and automatically eliminates the interference of lead impedance; Combined with the entered rated voltage and rated capacity, the microcontroller automatically converts and displays on the same screen: measured short-circuit impedance percentage (Zk%), impedance value (Ω) and the error percentage (△Zk%) compared with the standard impedance on the nameplate.
If the absolute impedance error of any phase exceeds the 2% specified in the regulation, the instrument can accurately warn of potential risks of severe geometric displacement or mechanical deformation of the winding on that phase.
Detect major faults with a small power supply, lightweight, safe and reliable. The HZZH-5 makes on-site judgment of transformer winding deformation at substations as convenient and efficient as routine inspection!